Improvements Along Main Street


Improvements will take place on East Main Street/Newark Christiana Road from Marrows Road to West Main Street – Elkton Road

___________

Improvements include the replacement of the street and sidewalk asphalt and pavement, repaving curbs, drainage improvements, signal upgrades, curb extensions, pavement markings and signage.

Project Overview

 


Current Construction Activities:

All activities weather dependent:

June 17-July 1: Phase 3 (Main Street left lane from Washington Street to Chapel Street)—Road construction and curb ramps. Tentative switch to Phase 4 week of June 24.

June 17- July 1: Switch to Phase 8 (Main Street left lane from east of S. College Ave. to Trabant Garage)---Drainage and roadwork

NIGHTWORK: Sunday June 16 into Monday June 17---Water line work (requires water shutdown overnight)

NIGHTWORK: Wednesday June 20 (2 am – 7am) or Thursday June 21 (2am – 7am)…..entrance to Trabant Garage closed.